What will happen after June 3 if the bond passes?

The citizen’s oversight committee needs to be formed within 60 days. Hiring of a project manager for the middle school project, establishing the educational specifications and site planning details, obtaining State approvals, and then obtaining construction bids will likely consume the remainder of the 2008-2009 school year. Construction (demolition!) should start at the middle school in June 2009. Construction should last around 18 months with students using the new facilities by January 2011. After that, decisions will be needed regarding the next project(s).